TEL T310 (Woh Hup - Shanghai Tunneling Engineering Co JV)
Awarded by joint venture between Woh Hup and Shanghai Tunneling Engineering Co for Land Transport Authority (LTA) – Thomson-East Coast Line (TEL) – T310 project
LTA awarded the construction of Bayshore station to a joint venture between Woh Hup and Shanghai Tunneling Engineering Co. This involved the construction of the structure of the station, as well as two pairs of tunnels to Siglap and Bedok South stations.
Jenmon was then appointed by Woh Hup and Shanghai Tunneling Engineering Co to design, supply, deliver, install, test and commission 2 units of 12.5 ton Gantry Cranes to aid in this project. By having to ensure that the Gantry Crane was able to travel across the ‘cross track’ smoothly, and that there was good coverage of the anti-collision sensors to prevent oncoming cranes from colliding into one another, this made the project exceptionally complex and unique.
Jenmon’s Project and Design team had several discussions and correspondences with the customer to ensure that the cranes met the safety requirement. Monthly maintenance was also carried out throughout the entire duration of the project.
This project counts as the 2nd purchase from Shanghai Tunneling Engineering Co who has previously purchased 1 unit of 12.5 ton Gantry Crane for the LTA project – T225 Shenton Way station. This shows our constant emphasis on our Core Values, one of which is to foster long-term relationships with our customers, so as to ensure long-term continuity and success.